Operational Update 2019-05-02

Operational Update

As of 5/2/2019

Transportation status

  • Independence Parkway was opened to all traffic on Friday evening, April 26.
  • The PTRA resumed normal service April 29.

Terminal Operational Status

  • ITC Continues to make progress to restore terminal operations.
  • All tanks in the impacted tank farm have been cleaned to the extent feasible. Clean-up efforts on the waterways are finishing and crews are demobilizing.
  • The wastewater plant discharge has been re-established.
  • The Shoreline Assessment was completed for ITC’s docks, with the exception of docks 4, 5, and 8.
  • Once marine activity is safely and successfully re-established, we will begin resuming rail traffic followed by truck activity.

Actualización operativa 2019-05-02

Actualización operacional

A partir del 5/2/2019

Estado del transporte

  • Independence Parkway se abrió a todo el tráfico el viernes 26 de abril por la noche.
  • El PTRA reanudó el servicio normal el 29 de abril.

Estado Operacional de la Terminal

  • ITC continúa avanzando para restaurar las operaciones de la terminal.
  • Todos los tanques en el parque de tanques afectados se han limpiado en la medida de lo posible. Los esfuerzos de limpieza en las vías fluviales están terminando y los equipos se están desmovilizando.
  • La descarga de la planta de aguas residuales ha sido reestablecida.
  • La Evaluación de Shoreline se completó para los muelles de ITC, con la excepción de los muelles 4, 5 y 8.
  • Una vez que la actividad marítima se haya restablecido de manera segura y exitosa, comenzaremos a reanudar el tráfico ferroviario seguido de la actividad de los camiones.